Lightning Protection Studies
PROJECT: Lightning Protection System Risk
Cell was engaged by Mount Isa Mines to undertake a risk assessment for the Main Depot AMEX Plant & Magazine in accordance with Australian Standard AS1768:2021.
This included the following:
– Inspection of existing UPS facilities.
– Continuity tests.
– Soil resistivity tests.
– Individual and overall earthing tests.
Approximate Value: $30,000